CYA performed verification testing on the connection to the new oxygen underground piping, leading up to a new building valve to serve the project site.
The project included verification testing of a new medical air compressor system, three new zone valve box assemblies, area alarm panel, and outlets on booms in Pre/Post Op and the Minor Procedure rooms.